Tel: 01884 242554 | Mobile: 07774 136239 | Fax: 01884 242663 | Email:

Projects

John Luffman Trading has undertaken and successfully completed numerous projects. A few examples are detailed here. Please click on the photos for a closer look.

Tesco Braunton

View over the site progress [Tesco Braunton]

JLT is contracted to complete a new development for Tesco stores in partnership with Costains. Work completed includes new adopted roads, enabling works, engineering and street furniture including tarmac work. Due for completion end of September in 96 days.

The value of the contract is £2 million.

ASDA Bideford

Ecavator at work [ASDA Bideford]

JLT is working on a new build for ASDA stores in Atlantic Village in partnership with Midas Retail. JLT was awarded 2 contracts, one for engineering and one for groundwork and civil work including drainage, store frame and walls.

The contracts have a combined value or £1.8 million and was completed on time in June 2008.

Kennedy Way, Tiverton

Photos coming soon [Kennedy Way]

JLT was instructed to carry out all enabling and and civil works for two new retail outlets in Tiverton to the value of £500,000. The project was completed on time in spring 2008.

Opportunity Okehampton

View over the site progress [Opportunity Okehampton]

JLT is contracted to complete groundworks and roadworks for a number of new business units. It was completed in March 2008.

Tesco Ilfracombe 2005-2006

View of the Side Elevation [Tesco Ilfracombe]

With exception of the steel frame, JLT were given the complete contract. This included carrying out the earthworks, ground works, tarmacing, streetlights, steel furniture and fencing.

JLT moved 65,000m cubed around the site and moved 25,000m cubed off site. The rock face was cut back by 4m which was 32m up a vertical face and put in attenuation ponds and tanks.

This contract was with Costain's and had a value of £3.4 million and the work was completed within 22 weeks from start to finish.

Tesco Tiverton 2004-2005

Ecavators at work [Tesco Tiverton]

This contaminated brownfield site was a former concrete yard on the outskirts of Tiverton town centre. To reduce environmental impact, all materials were processed on site and then used to form the foundations of the carpark and the platform for the building

JLT simultaneously completed flood alleviation works for the Environment Agency within the allotted contract time of 26 weeks.

JLT was awarded the contract which had a value of £3.18 million by Midas.

Met Office, Exeter 2003

An excavator at work [Met Office]

During a 2 year contract period with Costain Skanska. JLT was tasked with completing a number of projects during the final construction stages of the main building.

JLT completed minor earthworks, car parks, ponds and general groundworks along with placing fuel tanks.